Your customer is renovating the whole house

In a full renovation your bank is part of the subsidy: you apply for KfW's efficiency house loan, before the work starts and with the confirmation of an energy efficiency expert. The planning takes time before the first craftsman arrives.

How to recognize the situation

  • Your customer has bought or inherited an unrenovated house and wants to get everything done before moving in.
  • The energy certificate states efficiency class F, G or H.
  • Roof, facade, windows and heating are all due at the same time.
  • Your customer names a six-figure renovation sum or asks about the KfW loan for the efficiency house.
  • An architect or a construction company is involved, but no energy consultant.

What your customer needs now

Your customer first needs a decision on the subsidy route, because it determines the planning, the application and the financing: KfW's efficiency house loan through your bank, or grants for single measures in steps.

For both routes they need an energy efficiency expert, and for both the rule is: first plan and apply, then place orders.

What customers ask in this situation

  • What does it cost to renovate the whole house, and how much in subsidies is there?
  • Which efficiency house level can my house reach?
  • A loan with a repayment grant, or grants for single measures?
  • Do I have to do everything at once?
  • When can the craftsmen start?

The recommended path with NOVO

A full renovation begins with the planning. The path leads from the first assessment through the roadmap to the confirmation you need for the loan application.

  1. Step 1

    Energy check

    The check shows in a few minutes the efficiency class and the condition of the components, after a purchase already with the details from the property listing. That makes clear how far the house is from an efficiency house.

    Cost
    free
    Duration
    a few minutes
    Result
    A first assessment of the house
    Go to the energy check
  2. Step 2

    Free initial consultation

    The energy consultant clarifies the goal, the budget and the schedule and which subsidy route suits the house: efficiency house or single measures in steps.

    Cost
    free
    Duration
    appointment booked online
    Result
    A clear next step and a non-binding offer
    Book an appointment
  3. Step 3

    Individual renovation roadmap (iSFP)

    The roadmap surveys the house and shows which target state can be reached and what it costs. Its data go into the specialist planning; for the route through single measures it opens the iSFP bonus.

    Cost
    from €995 own share after the grant
    Duration
    a few weeks from the order
    Result
    Roadmap, investment need over the years, access to the iSFP bonus
    Go to the renovation roadmap
  4. Step 4

    Funding support

    For the efficiency house, funding support means energy-related specialist planning and construction supervision: NOVO issues the confirmation for the application (BzA) for your bank and, once the work is finished, the confirmation after completion, which proves the level reached.

    Cost
    from €250 own share, subsidized by the federal government
    Duration
    from the check of the offers to the proof
    Result
    Application, approval and payout of the subsidy
    Request an offer

Subsidies and deadlines

There are two routes. The first is KfW's efficiency house loan of up to €150,000 per residential unit, applied for through the financing bank, before the work starts and with the confirmation for the application (BzA). The second is grants for single measures, step by step: 15% for the building envelope and the KfW heating subsidy.

For the efficiency house, the repayment grant depends on the level. It is up to 15% of the loan; the levels 70 EE and 85 EE receive the loan without a repayment grant. For the buildings that are among the worst in energy terms there is a bonus of 10 percentage points at the levels 40, 55 and 70.

The level that is subsidized is the one stated in the BzA and covered by the commitment. It must be right before the loan contract is signed.

In practice the energy consultant often recommends the route through single measures. The building envelope is spread over two or more calendar years, the heating goes through KfW's heating subsidy, and the supplementary loan through your bank comes on top. The efficiency house loan pays off above all when a level with a repayment grant is within reach. This decision belongs before the first application.

  • Renovation to an efficiency houseup to €150,000

    KfW loan per residential unit, with a repayment grant of up to 15% depending on the level reached. The levels 70 EE and 85 EE receive the loan without a repayment grant. Application through the financing bank, before the work starts.

    Source: KfW: residential buildings, loan (261), in German
  • Grant for insulation, windows and doors15%

    Federal Funding for Efficient Buildings (BEG), single measures. Up to €30,000 are eligible for the first residential unit, per building and calendar year. Application before the project starts, with an energy efficiency expert.

    Source: BAFA: single measures on the building envelope, in German
  • iSFP bonus+ 5 percentage points

    Since 21 July 2026 only when the eligible investment reaches the ceiling that applies without an iSFP (€30,000 for one residential unit), and only on the part above it. With the bonus, the ceiling for the first residential unit rises to €60,000. The measure must be carried out within 15 years after the iSFP.

    Source: BAFA: single measures on the building envelope, in German
  • Grant for the energy consulting with iSFPup to €650

    50% of the consulting fee, at most €650 for one- and two-family houses and €850 from three residential units. The guideline in force runs until 31 December 2026; no successor had been published when this page was checked.

    Source: BAFA: energy consulting for residential buildings, in German
  • Specialist planning and construction supervision50%

    Grant toward the fee of the energy efficiency expert, eligible up to €5,000 for one- and two-family houses.

    Source: BAFA: specialist planning and construction supervision, in German

Your part in the advice

  1. Get involved early

    When a customer buys or inherits, ask about the scope of the plans. If several components and the heating are due at the same time, the energy consulting comes before the first craftsman.

  2. Invite

    Choose the invitation “Free iSFP initial consultation & Schnellcheck” in the partner cockpit. After a purchase, the renovation roadmap can begin as soon as the purchase contract is notarized.

  3. Check the level, apply for the loan

    You apply to KfW for the efficiency house loan, before the work starts and with the BzA. Compare the level in the BzA with your customer's planning and cost calculation before the contract is signed.

  4. Set up the overall financing

    Bring the KfW loan, your own financing for the rest and, after a purchase, the purchase price together in one plan. The repayment grant is credited only after the level reached has been proven.

  5. Allow time

    Before the first binding order come the roadmap, the specialist planning, the craftsmen's offers, the BzA and the loan commitment. Align the drawdown deadlines and the period free of commitment interest with that.

Invitation in the partner cockpitFree iSFP initial consultation & Schnellcheck

The way in for everyone who owns a house and wants to do something about it: your customer fills in the Schnellcheck and then books the free initial consultation themselves.

Conversation opener and objections

Conversation opener

Do you want to renovate the house step by step, or in one go before you move in?

  • Your customer saysThe craftsmen are ready, I want to start next month.

    Your answerThen the sequence matters. The KfW loan must be applied for before you place binding orders, and for the application I need the energy consultant's confirmation. You can prepare orders with a subsidy condition.

  • Your customer saysMy architect is taking care of that.

    Your answerGood, then the site management is settled. The KfW loan also needs an energy efficiency expert from the federal list of experts, who calculates and confirms the level. If your architect is not entered there, the energy consultant takes that on.

  • Your customer saysAn efficiency house is too much effort for me, I will only do what is necessary.

    Your answerThat can be the right decision. Have both routes calculated once: what the bare necessities cost, what the efficiency house costs and which subsidies come with each. The roadmap obliges you to nothing.

The financing occasion

This situation produces the largest financing volume of all: KfW's efficiency house loan of up to €150,000 per residential unit, applied for through your bank, and your own financing for everything that is above that or not eligible.

After a purchase, the purchase price and the renovation come together. Families with a child who buy a house of efficiency class F, G or H can also use the KfW loan for the purchase of an existing home.

If your customer chooses the route through single measures, KfW's supplementary loan is available after each grant commitment. The renovation roadmap then shows which amounts fall due in which years.

Pitfalls

  • The wrong level in the BzA: what has not been applied for and committed is not subsidized. A correction after the commitment as a rule means a new application.
  • Binding orders before the loan application put the subsidy at risk, including orders for individual trades that are placed in advance.
  • The statutory 65 percent rule no longer applies, but as a condition of the efficiency house loan a minimum share of renewable energy in the heat supply still does. Clarify early whether the planned heating meets it.
  • Energy-related construction supervision is not site management. Who coordinates the trades and accepts their work is something your customer arranges separately.
  • An energy certificate for the state after the renovation can only be issued once the work is finished. Before the loan decision, the BzA documents the planned level.
  • A customer who already owns the house needs the invitation to the initial consultation, not to the renovation report. The report is meant for the purchase decision; more under buying an existing home.

Frequently asked questions

Does NOVO issue the confirmation for the application (BzA) for the efficiency house loan?

Yes, as a separate service within the funding support and only after the building has been calculated. The BzA cannot be issued at short notice before a bank appointment. So report the need early, ideally in the initial consultation. On this basis you apply to KfW for the loan.

What happens if the house reaches a better level than applied for?

That is allowed but does not automatically bring a higher subsidy. The level that counts is the one stated in the BzA and covered by the commitment.

Does my customer have to renovate everything at once?

No. For the efficiency house loan, the level in the commitment must be reached. A customer who renovates in steps uses grants for single measures; the renovation roadmap shows the order and obliges them to nothing.

May my customer commission craftsmen before the loan application?

The application must be filed before the work starts. As alternatives, KfW names a contract with a condition precedent or a condition subsequent, or a documented advisory conversation with the financing partner. So document your advisory conversation.

How long does it take until construction starts?

From the order to the finished renovation roadmap it usually takes a few weeks. Then come the specialist planning, the craftsmen's offers, the BzA and your loan application. Advise your customer to start planning as soon as they are the owner.

Can the efficiency house loan be combined with other subsidies?

The supplementary loan belongs to the route through single measures because it requires a grant commitment. The tax reduction under Section 35c of the Income Tax Act is excluded for measures that receive a subsidized loan or a grant. How measures can be divided between the routes is for the energy consultant to clarify before the first application.

Is the construction supervision subsidized?

Yes. With the efficiency house loan, through an additional loan amount with a repayment grant, up to €5,000 for one- and two-family houses. For single measures, BAFA pays a grant of 50% toward specialist planning and construction supervision.

What happens next

  • Your bank works with NOVO

    Invite your customer in the partner cockpit and follow every step there.

    Go to the partner cockpit
  • Your bank is not a partner yet

    The simulator, the cockpit and the energy consulting can become part of your advice. We show you how.

    NOVO for companies
  • You own a home yourself

    With the free energy check you see in a few minutes where your house stands.

    Start the energy check
Need help?
We're happy to help!Book a phone call with usPrefer email? Contact us here.

We use cookies and similar technologies to analyze the use of our website and to fix errors.

If you consent (“Accept all”): In addition to the necessary measurements, AWS CloudWatch RUM sets cookies and records your session to diagnose errors. All entries and texts are already masked in your browser.

If you decline (“Necessary only”): With AWS CloudWatch RUM, we only record load times, errors and the pages you visit, without cookies and without session recording. For this, RUM stores a technical identifier in your browser.

You can find more details in our privacy policy and in the legal notice. You can withdraw your consent at any time via “Privacy settings” at the bottom of every page.